Turnout sleepers in a steelwork in Salzgitter
FACTS
- Location: Steelwork Salzgitter, Deutschland
- Client: Verkehrsbetriebe Peine-Salzgitter GmbH
- Products: STRAILway turnout slepper
- Length/Quantity: 89,3 running metres /20 pieces
- max. Axle load: 37,5 t
- max. Speed: 25 km/h
- Conditions: Rail 54E4
- Period: May 2018
ADVANTAGES
- Service life > 50 years
- Particularly resistant to all environmental influences
- Suitable for heavy loads
- No working in of the ribbed plate
- No stripping of screw heads
- Excellent screw extraction force
AT A GLANCE
Salzgitter Flachstahl GmbH, a subsidiary of the Salzgitter Group, was looking for new sleepers for the works railway between the blast furnace and the rolling mill. Around 15 million gross tonnes of load roll over this track, including the turnouts, every year.
Previously, wooden sleepers were used, but they had to be replaced every five to seven years. The requirements for the new sleepers were therefore primarily: easy maintenance, durable, suitable for heavy loads.
The decision was made in favour of the STRAILway polymer sleeper, as it meets all the requirements and also provides an all-round carefree package, so to speak.
It is not necessary to work gravel and the ribbed plate into the STRAILway polymer sleeper, screws do not have to be retightened, and should a screw break off in exceptional cases, the sleeper can be repaired and does not have to be replaced.
The STRAILway polymer sleepers at the Salzgitter steelworks have been in use since 2018 and are still as good as new.
Picture 1: Since 2018, the STRAILway polymer sleepers have been in use at the steelworks in Salzgitter.
Picture 2: The durable STRAILway polymer sleepers are ideally suited for heavy-duty turnouts and are maintenance-free.
Picture 3: Prefabricated heavy-duty turnout with STRAILway polymer sleepers.