First installation in Guinea

FACTS

    • Client: COLAS RAIL
    • Location: Guinea-Conakry
    • Route: Railway kilometre
    • Products: STRAIL 1,200 inner and outer panels with kerbstones
    • Quantity: 10 single track level crossings, 4 double track level crossings
    • Length: Between 6 and 13,2 m
    • Special features: 1 level crossing with 200 m radius
    • Period: end of 2018 till beginning of 2019

 

ADVANTAGES

  • Quick and easy installation / removal
  • Adaptable to almost all types of tracks (rails, sleepers and fastening)
  • Lock-tight-system: Modular system consisting of individual panels linked together
  • Strong road connection with T-kerbstones
  • Anti-slip „pyramid“ surface

 

AT A GLANCE

For Highest Demands > in 2015 was STRAIL FRANCE contacted to provide crossings for the operation on a mine site.

High axle loads, extreme climate condition, just a few characteristics our level crossings have to withstand at the mine.

COLAS RAIL France, experienced with the installation of STRAIL systems, was present in Guinea-Conakry to assist local teams. So no STRAIL technician was needed.

Due to the good work in advance, the installation was carried out smoothly, by end of 2018.

Everything works perfect until today and Colas is very pleased with their STRAIL level crossings.

Picture 1: Finished Level crossing.